How a driveway is installed, step by step
A driveway goes in as seven steps: set out, dig 200 to 250 mm, lay geotextile, compact 150 mm of Clause 804, set kerbs and drains, lay the surface, and leave it to cure. Tarmac takes 2 to 3 days on site and cobblelock 3 to 5 days.
What happens on each day, how long each surface takes, and when you can park on it again.
Free, no obligation. One local contractor prices it, not five.
- 2 to 3 dayson site for a tarmac or SMA drive
- 3 to 5 dayson site for cobblelock
- 24 to 48 hoursbefore cars go on new tarmac
- 200 to 250 mmdug out before any stone goes in

The seven steps, in order
- Set out and check services. The area and levels are marked, and gas, water, electricity and drain covers are found before a bucket goes in the ground.
- Dig out. Grass, topsoil and soft ground are removed to 200 to 250 mm, deeper where the ground is soft. Spoil leaves by grab lorry at €350 to €650 a load.
- Geotextile. A woven membrane is rolled over the formation and lapped at the joints, so clay cannot work up into the stone.
- Sub-base. 150 mm of Clause 804 is spread and compacted in two layers. The falls are set here, not in the surface.
- Kerbs, drains and covers. Edging is bedded and haunched in concrete. Channel drains, at €85 to €155 a metre, and recessed trays for manholes are set to the finished level.
- Surface. Tarmac is laid hot and rolled. Blocks are laid on a sand bed, cut in at the edges, compacted and sanded. Tar and chip is sprayed, chipped and rolled.
- Cure and tidy. The site is swept, and the driveway is kept clear for as long as the surface needs.
Steps two to four are the part that cannot be seen afterwards and the part a low quote trims. Sub-base and excavation gives the specification to ask for.
Price my driveway
Four quick taps and our price shows before we ask for a phone number. One local contractor rings you, not five.
Tarmacadam or SMA asphalt, 50 to 100 m², full dig-out and Clause 804 sub-base: €3,300 to €9,000, excavated and laid.
How the price is worked out
The range reflects going Irish per-m² driveway rates for that surface, area band and groundwork depth. Full dig-out ranges cover 200 to 250 mm excavation, Terram geotextile membrane, 150 mm compacted Clause 804 stone (or permeable Type 3 stone for resin bound) and the finished wearing course. Selecting ACO drains and kerbing adds linear channel drainage, concrete-haunched edging and soakaway work. Grab-lorry spoil haulage, recessed manhole trays, steps and council footpath dishing depend on site access and are priced in writing after a contractor measures your drive.
Days on site, and when you can drive on it
Tarmac or SMA
- Time on site
- 2 to 3 days
- Ready for cars
- 24 to 48 hours
Cobblelock
- Time on site
- 3 to 5 days
- Ready for cars
- Immediate once compacted and sanded
Tar and chip
- Time on site
- 1 to 2 days
- Ready for cars
- Light traffic same day; avoid dry steering for 2 weeks
Resin bound
- Time on site
- 2 to 4 days
- Ready for cars
- 24 to 48 hours for cars
Concrete
- Time on site
- 3 to 5 days (plus curing)
- Ready for cars
- 7 days for cars, 28 days full strength
Those are working days for a typical front drive. Wet weather stops tarmac, tar and chip and resin, and frost stops concrete. Block paving and groundworks carry on in most conditions, so a week with poor weather stretches some jobs and not others.
A resurface over a sound base skips the dig and is shorter again: see resurfacing against full excavation.
What to have ready before the crew arrives
- Cars and access. Park on the road from the first morning. The drive is out of use until the surface has cured.
- Neighbours. A grab lorry and a tarmac lorry will stand on the road for a time. A word in advance saves a row.
- What is underground. Tell the contractor about any pipe, cable, tank or old drain you know of, and where the water shut-off is.
- Ducts. If a gate motor, lights or a car charger are likely later, have empty ducts laid under the sub-base now.
- The kerb. If the entrance is being widened, permission and the road opening licence come first. Dishing the footpath is a separate job.
- The quote. Dig depth, stone depth, surface thickness, spoil removal and VAT at 13.5% should each be written down.
Entrance rules are in planning and footpath dishing. Prices by surface are on driveway cost per m², and edging is in edging and borders.
Related driveway guides
Resurfacing vs full dig-outWhen a 35–40 mm overlay holds up and when soft subsoil or cracking forces full excavation.
SuDS drainage & ACO channelsKeeping driveway runoff off the public footpath with ACO drains, soakaways and correct falls.
Tarmacadam & SMA asphaltDense black SMA vs standard tarmac, roller compaction and €60–€95/m² build-up.
Cobblelock & block paving60 mm pavers, 90-degree herringbone lock, sharp grit sand and granite borders.
Imprinted & brushed concreteMesh-reinforced C30/35 slabs, saw-cut expansion joints, sealer care and frost resistance.
Driveway prices per m²Complete Irish cost guide across all six surfaces, spoil skips, kerbing and 13.5% VAT.Installation questions
How long does it take to install a driveway?
Tarmac or SMA takes 2 to 3 days on site, cobblelock 3 to 5 days, tar and chip 1 to 2 days and resin bound 2 to 4 days. Concrete takes 3 to 5 days (plus curing).
How soon can I drive on a new driveway?
Tarmac: 24 to 48 hours. Cobblelock: immediate once compacted and sanded. Tar and chip: light traffic same day; avoid dry steering for 2 weeks. Concrete: 7 days for cars, 28 days full strength.
How deep is a driveway dug out?
200 to 250 mm below the finished level on ordinary ground, to make room for 150 mm of Clause 804 and the surface. Soft or wet ground is dug deeper until it is firm.
Can a driveway be laid in winter?
The dig, the sub-base, kerbs and block paving can go ahead in most winter weather. Tarmac, tar and chip and resin need a dry day, and concrete is not poured in frost. Expect a job to be booked around the forecast.
All driveway pages, guides and counties
Driveway surfaces
Prices, build-up & rules

Check your driveway price before anyone calls
Pick your surface, rough area in m² and base prep. When you want a written site quote, your outline goes to a single driveway contractor in your county.